Calculate critical path and task float

Identify sequence bottlenecks and calculate total float to see which delayed tasks directly shift your final delivery date.

You getCritical Path Summary, dependency & Float Table and risk Hotspots

Prompt

Prompt
Act as a senior project scheduler. Analyze the provided project tasks, durations, and dependencies to find the critical path and calculate float.

- Trace the longest dependent path to determine the overall minimum project duration.
- Calculate early start, early finish, late start, late finish, and total float for every task.
- Identify zero-float tasks that threaten the end date if delayed by a single day.
- Flag any circular dependencies or missing predecessors.

Output format:
1. Critical Path Summary (total timeline and sequence of zero-float tasks)
2. Dependency & Float Table (Columns: Task, Duration, Predecessors, Early Start/Finish, Late Start/Finish, Total Float, Critical Y/N)
3. Risk Hotspots (top 3 scheduling risks and recommended buffer placements)

My task list is below:

Example output

Example for: software release with 6 core development tasks

  1. Critical Path Summary
    Total Timeline: 18 working days.
    Critical Path Sequence: Task A (API Schema) -> Task C (Core Engine Build) -> Task E (Security Audit) -> Task F (Production Deployment).
  2. Dependency & Float Table
TaskDurationPredecessorsES / EFLS / LFTotal FloatCritical
A: API Schema3 daysNoneDay 1 / 3Day 1 / 30 daysYes
B: Frontend Wireframes4 daysNoneDay 1 / 4Day 5 / 84 daysNo
C: Core Engine Build8 daysADay 4 / 11Day 4 / 110 daysYes
D: UI Implementation4 daysB, ADay 5 / 8Day 9 / 124 daysNo
E: Security Audit5 daysCDay 12 / 16Day 12 / 160 daysYes
F: Production Deployment2 daysD, EDay 17 / 18Day 17 / 180 daysYes
  1. Risk Hotspots
  • Security Audit has zero float and relies on a clean Core Engine handoff; slip here moves day 18 directly.
  • UI Implementation has 4 days of float, but late changes to API Schema will erode this margin quickly.
  • Add a 2-day feeding buffer between Core Engine completion and the Security Audit kickoff.
Written by AI from this prompt. Your results will vary.

Paste your task list, estimated days, and dependency links after the prompt in ChatGPT, Claude, or Gemini. As a follow-up, ask the model to re-run the calculation assuming your most constrained task takes twice as long.

Make it repeatable

Keep using this prompt without pasting it in every time.

Keep exploring

More in Project Management
Project Management

Level team capacity using schedule float

Balance team workloads across sprints by shifting non-critical tasks into available schedule slack. Use this when some teammates are overbooked while critical path float remains.